Updated January 6, 2025
- The ballot initiative to approve debt related to the 2023 Spring Canyon Local Improvement District (LID) was approved by the voters in the LID on November 5, 2024, with a debt cap of $19,580,000.
- The County plans to issue an RFP for financial services in January 2025, with proposals due in February 2025.
- Once financing is confirmed, preliminary design is scheduled to begin on the project with a target completion date of June 2025.
- Final design is scheduled for completion in December 2025 and bids for construction will be obtained in early 2026.
- Construction is expected to begin in 2026 and be completed in 2027.
- Based on this timeline, the first assessment of property owners will be due in 2028.