Updated June 6, 2025
Roadway paving operations have wrapped up for the US 85 project after completing multiple weeks’ worth of paving in just a few days last month. The remaining operations for the overall project include permanently striping the roadway, completing pedestrian trail connections, installing new signage, landscaping installation and signal/lighting activation.
During overnight shifts next week, crews will implement right lane closures on C-470 below the new US 85 bridge to install under deck lighting.
Watch a video to see how CFIs work
See the “Schedule” section below for more detailed information on traffic impacts. For background information prior to construction, visit US85DouglasCounty.com